Construction price
A. PRICE OF ROUGH STRUCTURE PACKAGES:
Customers can choose one of the following construction packages:
No. | Item & Description | Basic package | Standard package | Advanced package |
---|---|---|---|---|
I | Total price | 2,800,000 VND/m2 | 3,000,000 VND/m2 | ≥ 3,500,000 VND/m2 |
II | Applying conditions | |||
1 | Materials can conveniently gathering at works by small trucks | Ok | Ok | No |
2 | Conditions of total building area | ≥ 400 m2 | 200 ÷ 400 m2 | ≤ 200 m2 |
3 | Conditions of locating at between two adjacent houses | In middle of existing houses | Not meet | Not meet |
III | Materials of package | |||
01 | Steel of VINAUSTEEL/VIETNAM-ITALY STEEL Co. | X | X | X |
02 | Crushed rock 1×2, 4×6 from Hoa Cam | X | X | X |
03 | Sand from Tuy Loan village | X | X | X |
04 | Cement Kim Đinh/Hoang Thach/Nghi Son Co. | X | X | X |
05 | Commercial concrete of Dang Hai co. | X | X | X |
06 | Clay bricks of Dai Hiep factory, Dai Loc, Quang Nam province | X | X | X |
07 | Hosepipe of Binh Minh Plastic co. | X | X | X |
08 | Electrical cable/wire of CADIVI co. | X | X | X |
09 | Wires for cable TV, ADSL, phone: SINO co. | X | X | X |
10 | Rigid conduit in the concrete floor: VEGA co. | X | X | X |
11 | Flexible conduit for protecting electrical wire: SINO co. | X | X | X |
12 | Waterproofing chemicals for floor : Sika co. | X | X | X |
13 | Formwork: film wood, steel column | X | X | X |
IV | Jobs of pakage | |||
01 | Keep work site clean, locating the center of structures and the standard level | X | X | X |
02 | Earthwork of: foundation, septic tank, underground water tanks; transporting rubble from the site | X | X | X |
03 | Pressing reinforced concrete piles, Reinforcing the foundation by pressing piles | No | No | X |
04 | Smashing pile head | X | X | X |
05 | Pouring concrete lining of foundation, 4×6 rock, grade 100 #, 100mm thick | X | X | X |
06 | Production and erecting formwork, reinforcing steel and pouring concrete: simple foundation, foundation beam | X | X | X |
07 | Production and erecting formwork, reinforcing steel and pouring concrete: strip foundation | No | No | X |
08 | Production and erecting formwork, reinforcing steel and pouring concrete: columns, beams, floor, stair | X | X | X |
09 | Placing outside walls, division walls in the whole project | X | X | X |
10 | Erecting plumbing, electrical wires | X | X | X |
11 | Roof deck and WC floor waterproofing | X | X | X |
12 | Plastering for all walls | X | X | X |
13 | Screeding for all floors | X | X | X |
14 | Tiling for all faces (not including tile and sealing grout) | X | X | X |
16 | Installing electrical systems and lights (including wires but not including electrical equipments and lights) | X | X | X |
17 | Electrical equipments, lights, tiles and sealing grout | No | No | X |
18 | Cleaned daily work | X | X | X |
19 | Basic cleaning work before handover | X | X | X |
Notes:
- Package construction means the customer is only responsible for construction permits, permission to use the pavement. After handing over the ground and power / water to us, we will do all the rest for construction until completion of the entire works or a part of works already concluded that in the construction contract.
- Please see how the area will be used to determine the total cost of the package at the section of “Entire building construction price”.
B. ENTIRE BUILDING CONSTRUCTION PRICE:
Customers can choose one of the following construction packages:
TT | Basic package | Standard package | Advanced package |
---|---|---|---|
I | 4.900.000 VND/m2 | 5.500.000 VND/m2 | 6.500.000 VND/m2 |
01 | Including standard rough structure package | Including standard rough structure package | Including standard rough structure package |
02 | Inax sanitary equipments, lavatory bowl C117 – two blocks | Inax sanitary equipments, lavatory bowl C117 – two blocks – two flushing modes | Advanced Inax sanitary equipments, one block lavatory bowl |
03 | Taicera tiles, tiles 60×60 for floor, tiles 30×45 for bathroom walls | Taicera tiles, tiles 60×60 for floor, tiles 30×60 for bathroom walls | Boao tiles, tiles 60×60 for floor, tiles 30×60 for bathroom walls, Laminate wood for bedroom floor |
04 | Economic Maxilite paint for the whole house | Dulux paint for front faces, Maxilite paint for interior faces | Dulux paint for the whole house |
05 | Front doors with galvanized iron, powder coated; Aluminum glass doors for interior | Plastic doors with steel core at the front, interior doors making from cherry, PU coating | Natural wood doors for the entire house, PU coating |
06 | Thanh Hoa granite / chinese granite for treads and risers of stairs | Granite from An Khe, Gia Lai province for treads and risers of stairs | Treads and risers of stairs are coated with wooden panels, wooden handrail, PU coating |
07 | Lighting equipments are florescent lights 1.2m | Lighting equipments are downlight lights | Lighting equipments are downlight lights with light-emitting diode technology |
08 | Gypsum ceiling Vinh Tuong, applying only in the living room | Gypsum ceiling Vinh Tuong, applying in the entire house | Gypsum ceiling Vinh Tuong, applying in the entire house |
Applying conditions:
- Total floor area > 280 m2.
- The investor is responsible for providing power and water source for construction.
The case of additional costs:
- Total floor area ≤ 280 m2.
- Can not deliver materials conveniently to the site by small truck.
- Site locate in the area of market, the delivering of construction materials is interrupted or we have to gather materials at night.
- The above packages don’t include: reinforced foundation costs, tape foundation costs, costs for work related to concrete piles, bored piles, melaleuca piles, the basement walls with > 60cm deep; outside scaffolding for the entire works, geological survey costs, surveying costs, cost for power meter, new water supply.
The calculation to determine the area of packages:
Notes of above picture:
- S = Total area for calculating the total cost of a package (D ~ length, R ~ width).
- For basement depth greater than 0.6 m, then every 2 m depth will be calculated as a floor. Tiled roof above the concrete floor will be counted as a floor; corrugated roof above the roof deck will be charged 70% of the area. Not subtracting the area of the floor holes.